1807-17 GRAVOIS AV
| Application date | Nov 13, 2026 |
|---|---|
| Issue date | Nov 17, 2026 |
| Days to issue | 4 |
| Estimated cost | $5,000 |
| Project type | Addition |
| Structure type | 25 |
| First seen | 2026-11-18 12:41:47 |
Description
We will begin by temporarily remove plywood as needed and reinstall it before leaving each day. Reset loose bricks, drill 6 inches into the existing foundation to install rebar for reinforcement, install a 4-inch block base, and add brick for the finished appearance. Install wall ties to secure and reinforce the connection between the block an brick wall.