2922 PENNSYLVANIA AV
| Application date | Feb 5, 2026 |
|---|---|
| Issue date | Nov 12, 2026 |
| Days to issue | 280 |
| Estimated cost | $12,000 |
| Project type | New Const. |
| Structure type | 23 |
| First seen | 2026-11-13 13:17:24 |
Description
CONSTRUCT GARAGE PR PLNS
| Application date | Feb 5, 2026 |
|---|---|
| Issue date | Nov 12, 2026 |
| Days to issue | 280 |
| Estimated cost | $12,000 |
| Project type | New Const. |
| Structure type | 23 |
| First seen | 2026-11-13 13:17:24 |
CONSTRUCT GARAGE PR PLNS