6012-128 S BROADWAY
| Application date | Oct 28, 2026 |
|---|---|
| Issue date | Nov 3, 2026 |
| Days to issue | 6 |
| Estimated cost | $4,500,000 |
| Project type | Alteration |
| Structure type | 34 |
| First seen | 2026-11-05 11:54:22 |
Description
Project consists of the removal of existing casting equipment and the installation of a new casting line. Construction will include new structural foundations for the equipment as well as the build of a new motor control center room to operate the new equipment.